Scope
|
||
Accuracy of Estimates:
|
||
Order of Magnitude
|
Done during Initiating
|
- 25% to +75%
|
Budget Estimate
|
Done during Planning
|
-10% to +25%
|
Definitive Estimate
|
Done during Planning
|
- 5% to +10%
|
Project Planning Methodology
|
A structured approach used to guide the project team
during development of the project plan
|
Use Hard tools (Project Management Software) and Soft
tools (facilitated meetings)
|
CWBS
|
Contractual WBS
|
For Seller
|
OBS
|
Organization Breakdown Structure
|
Work components to Organization Units
|
RBS
|
Resource Breakdown Structure
|
|
BOM
|
Bill of Material
|
Manufacturing
|
PBS
|
Project Breakdown Structure
|
Same as WBS; used when WBS is used instead of BOM
|
Cost/Schedule
|
|||
Project Network Diagram – also called PERT (Program
Evaluation & Review Technique)
|
PDM – Precedence Diagraming Method aka AON – Activity
on Node
|
4 relations:
Finish to Start (Common)
Finish to Finish
Start to Start
Start to Finish (Rare)
|
|
PERT & CPM can be drawn only using ADM/AOA
|
ADM or Acitivity Diagraming Method
Aka AOA – Activity on Arrow
|
Use Dummies
Only one relation: Finish to Start
|
|
Hammock
|
When two activities meet
|
Portions of Network also called Fragnet/Subnet
|
|
GERT – Graphical Evaluation Review Technique
|
Loops & Conditional Branches
|
Probabilistic Treatment
|
|
PERT – drawan using AOA
|
Uses weighted average; is rarely used
|
For time or cost
|
|
CPM – drawn using AOA
|
Uses most likely estimate
|
Can have dummies
|
|
Duration Compression
|
Crashing – Putting more resource
Increases cost
|
Fast-Tracking – Doing in Parallel instead of Sequence
Rework and more risky
|
|
Monte-Carlo Analysis
|
Simulation for What-if Conditions
|
Does not use PERT formula; uses path convergence
|
|
Analogous Estimating
|
Topdown approach
|
Is a kind of Expert Judgement
|
|
Reserve
|
Contingency, Buffer
|
10% in general
|
|
Float/Slack = LS – ES or LF – EF;
also called Free Slack, Total Slack & Path Slack
|
Amount of time a task can be delayed without delaying
the successor
|
Critical Path tasks will have zero slack
|
|
Total Slack
|
Amount of time a task can be delayed without delaying
the project
|
||
Project Slack
|
Amount of time a project can be delayed without
delaying the externally imposed date
|
||
Lag
|
Waiting time between tasks
|
Concrete Curing Time
|
|
Lead
|
Successor task can start early
|
||
Network Diagram – For Dependency
|
Bar/Gantt Chart – Progress Reporting
|
Milestone – Status Reporting for Management
|
|
CV = EV – AC
|
+ ve Is good
|
- ve is bad (over budget)
|
|
SV = EV – PV
|
+ is good
|
- ve is bad (behind schedule)
|
|
CPI = EV/AC
|
CPI > 1 is good
|
CPI < 1 is bad
|
|
SPI = EV/PV
|
SPI > 1 is good
|
CPI < 1 is bad
|
|
EAC = BAC/CPI
|
Estimate At Completion
|
||
ETC = EAC - AC
|
Estimate to Complete
|
||
VAC = BAC - EAC
|
Variance At Completion
|
||
PV = FV/ (1+r) n
|
Present Value
|
Today’s value for future value
|
|
NPV
|
Net Present Value
|
Years included so go with $ amount (higher the better)
|
|
IRR
|
Internal Rate of Return
|
Higher the % the better
|
|
BCR
|
Benefit to Cost Ratio
|
Payback to Cost; > 1 is good
|
|
Payback Period
|
Time when you start getting returns
|
Lower the better
|
|
Opportunity Cost
|
NPV2 – NPV1
|
Return on choosing one over another
|
|
Sunk Costs
|
Expended Costs
|
SCORE Project 20 m
|
|
PERT = (P + 4ML + O)/6
|
Std. Dev = (P-O)/6
|
Variance = [P-O/6]2
|
|
+- 6 Sigma = 99.99
|
||
+- 3 Sigma = 99.73
|
||
+- 2 Sigma = 95.46
|
||
+- 1 Sigma = 68.26
|
||
Direct Cost
|
Project cost
|
Salary, Travel, Awards, Material
|
Indirect Cost
|
For group and for all projects; % of direct cost
|
Tax, Fringe Benefits, Janitorial Service
|
Fixed Cost
|
Does not change with work
|
Rental, setup
|
Variable Cost
|
Changes with work
|
Material, Wages
|
Crashing Cost
|
Find the difference between Crash Cost and Original
Cost
|
The lowest is the choice
|
Heuristics
|
Rule of Thumb
|
80/20
|
Quality
|
|
Design of Experiments
|
Tire/Wheel in a car
|
Benchmarking
|
Comparing with others
|
Ishikawa Diagram
|
Cause and Effect or Fishbone Diagram
|
Flow Chart
|
How elements flow through
|
Quality Audit
|
Part of QA – To check overall process
|
Inspection (review, walkthrough, audit)
|
Part of QC – To check specific deliverable
|
Control Chart
|
Upper and lower control limit;
Specification limits;
Baseline or mean;
Rule of seven;
Assignable cause;
Out of control
|
Paretto Diagram
|
A Histogram – 80/20: 80% of problems are caused by 20%
of causes
|
KAIZEN
|
Continuous Improvement
|
Variable – Characteristic like Shape, Wieght
|
Attribute – Measurement like inches, pounds
|
HR
|
|||||
RAM - Responsibility Assignment Matrix
|
War Room
|
||||
Resource Histogram
|
Resource Gantt Chart
|
||||
Fringe Benefits
|
Insurance, Bonus etc.
|
||||
Perks
|
Corner office, Executive Dining
|
||||
Conflict Management
|
|||||
Smoothing
|
Both agree or similarities and do not talk about
differences
|
also called Accommodating
|
|||
Forcing
|
Its my way
|
also called Competing, Assertive
|
|||
Withdrawal
|
I give up
|
also called Avoidance
|
|||
Compromising
|
Both give up little
|
||||
Confronting
|
Solve the problem
|
Also called Problem Solving or Collaborative
|
|||
Maslow’s Theory
|
Pyramid
|
Self Actualization
Esteem
Social
Safety
Physiological
|
|||
McGregor’s Theory
|
Theory of X & Y
|
X – Need to be watched
Y – Independent
|
|||
Herzberg’s Theory
|
Hygiene Factors
|
Motivating Agents
|
|||
Halo Effect
|
Engr -> PM
|
||||
Expectancy Theory
|
Awards <-> Work->
|
Achievement Theory
|
Importance of friendship and sense of camarederie in
work environment
|
||
Source of Conflict
|
|
||||
Communication
|
|||
Formal Written
|
Complex Problems, Charter/Plan, Distance
|
Informal Written
|
Memo, Email, Notes
|
Formal Verbal
|
Prezo, Speech
|
Informal Verbal
|
Meetings
|
Channels of Communication
|
N*(N-1)/2
|
Hi There,
ReplyDeleteVery Nice post on PMP Notes.That was very helpfull.keep posting